Map of Proposed Work 2022
Proposed Work 2022
Paving
Street
|
From
|
To
|
Status
|
Duke Street
|
Water St.
|
North Market St
|
Complete
|
Rufus Street
|
North Market St
|
Water St
|
Complete
|
Northumberland St
|
Myrtle St
|
Maddix North
|
Complete
|
Bernard Street
|
Burkeshire Dr
|
Lynda
|
Complete
|
Industrial Cr
|
Turn west end
|
Mill Cres W
|
Deferred |
Granville Street
|
Lefurgey Ave
|
Arnett
|
Complete
|
Pope Road
|
Duke St
|
283 pope rd
|
Complete
|
Granville Street
|
Arnett
|
Beaton Ave.
|
Complete
|
Pope Road
|
d/w 324 Pope
|
Duke St
|
Complete
|
Cass Av
|
Wright
|
To the end
|
Complete
|
Wright
|
MacEwen
|
Cass Av
|
Complete |
Groom
|
MacEwen
|
To the end
|
Complete |
Sidewalks
Street
|
From
|
To
|
Direction
|
Status
|
Duke St
|
Second St
|
North Market St
|
West
|
Complete
|
Poplar St
|
Duke St
|
343 Poplar
|
North
|
Complete
|
Water St E
|
Clarks
|
720 Water St E
|
South
|
Complete
|
Heather Moyse Dr
|
Marine terminal
|
Water St intersection
|
South
|
Complete
|
High St
|
Victoria Rd
|
KenMoore St
|
West
|
Complete
|
MacEwen Rd
|
Water St
|
601 Water St
|
East
|
Complete
|
First St
|
Spring St
|
Summer St
|
South
|
Complete
|
Jennifer St
|
322 Jennifer St
|
Highland St
|
West
|
Complete
|
Summer St
|
Pleasant St
|
Green St
|
East
|
Deferred
|
Belmont St
|
MacFarlane St
|
Eustane St
|
South
|
Deferred
|
Granville St
|
Rogers Av
|
Schurman Av
|
East
|
Deferred
|
Glenn Dr
|
South Dr
|
Tanton Dr
|
North
|
Complete
|
Curb and Gutters
Street
|
From
|
To
|
Direction
|
Status
|
Victoria Rd
|
Arcona St
|
Highland St
|
South
|
Complete
|
Market St
|
Duke St
|
Cedar St
|
South
|
Complete
|
Other Projects
Project
|
Status
|
Street construction – Brophy cul-de-sac
|
Complete
|
Storm Sewer – Glovers Shore rd
|
Complete |
Storm Sewer -Water St KFC
|
Complete |
Storm Sewer – King st
|
Complete
|
Storm Sewer – Cedar st
|
Complete |
Storm Sewer – Glenn
|
Complete
|
Storm Sewer – Hallie
|
Complete
|
Storm Sewer – Murphy
|
Complete
|
Storm Sewer – Bay
|
Complete
|
Water project – Central St
|
Complete
|
Sewer project – Cedar St
|
Deferred to 2023 |
Sewer project – Chandler Av
|
Complete |
Sewer Project – Saunders Av
|
Complete
|
Lift station - Reads Corner
|
Complete
|
For more information, contact:
Cindy Hierlihy
[email protected]
902-432-1262
City of Summerside, 275 Fitzroy Street, Summerside, PE, C1N 1H9